Using RCMs

Reliability Centered Maintenance (RCM) analysis provides a structured framework for analyzing the functions and potential failures for a physical asset in order to develop a scheduled maintenance plan that will provide an acceptable level of operability, with an acceptable level of risk, in an efficient and cost effective manner.

The basic steps for performing RCM analysis are:

  1. Create the project and set project properties

  2. Add items in the system hierarchy

  3. Perform equipment selection

  4. Add a new functional failure analysis

  5. Add functional failure analysis records

  6. Perform failure effect categorization

  7. Perform maintenance task selection and add a task

 

Quick Tour
Tour Intro   -   Repositories & Projects   -   Project Properties   -   Using FMEAs   -   Using RCMs   -   More Analyses & Tools

 

© 1992-2018. HBM Prenscia Inc. ALL RIGHTS RESERVED.

E-mail Link