Tasks

Simulation Diagrams

Multiple Tasks on the Same Block

Certain additional simulation assumptions apply when multiple tasks (i.e., corrective, preventive, inspection and/or on condition tasks) apply to the same block:

Tasks are prioritized as follows:

    1. Tasks based on events in a maintenance group, where the triggering event applies to a block

    2. Tasks based on system down

    3. Tasks based on events in a maintenance group, where the triggering event applies to a subdiagram

If there is also a task based on interval scheduled to occur at the same time, the interval-based task OR the task highest in this priority list may be performed.

If a failure or preventive task occurs during a non-downing inspection, and the corrective task or the preventive task has a restoration factor, and the inspection task has a restoration factor, then both restoration factors are used (compounded).

If a corrective task is scheduled to be performed upon inspection and a preventive task occurs first, the preventive task will restore the block.

If a corrective task is scheduled to be performed upon inspection and a failure or preventive task occurs during a non-downing inspection, the restoration is compounded.

 