Related Topics:

Quick Parameter Estimator

Wizard View

Quick Parameter Estimator Expert View

Follow the steps below to use the Expert view of the Quick Parameter Estimator (QPE):

Tip: If you are building an event occurrence or task duration model, you can treat an "unreliability" point as the probability that an event will occur or that a task will be completed by a specified time. For example, if you are modeling the probability of an event's occurrence and you believe that there is a probability of 30% that the event will occur before 150 hours, then you would enter 0.3 in the Unreliability field and 150 in the Time field.

 

© 1992-2013. ReliaSoft Corporation. ALL RIGHTS RESERVED.