Related Topics and Links:

Project Planner

Project Planner Timelines

Project Planner Gates

Each gate in the Project Planner has its own properties and a status that is determined based on its expected start/completion dates. Additional information about progress and resource usage is available in the summary panel.

To view the properties of a gate, double-click it, or select it and choose Project Planner > Gate > Edit Gate.

Gate Properties

Gate Status

The gate status (which is displayed in the summary panel and in the status bar) is determined based on the same logic used for action statuses, which takes into account the expected start/completion date and any actual dates. For example, a gate's status is "Past Start Date" if it hasn't started and it's too late to start by the expected date, while "Past Due" means it is too late to complete on time.

 

© 1992-2019. HBM Prenscia Inc. ALL RIGHTS RESERVED.

E-mail Link