The Resource Manager allows you to create, view, edit and delete resources in the project. The types of resources available in the Resource Manager depend on which Synthesis-enabled application you are using. For a list of which resource types are available in which applications, see Resources. To open the Resource Manager, choose Project > Synthesis > Resource Manager.
To use the Resource Manager, choose the type of resource that you want to work with in the navigation panel on the left side of the window. A table that displays all resources of the selected type will be shown on the right side of the window. You can limit the number of resources shown in the table using the Home > Filter > Maximum Display field. The limit can be adjusted in increments of 100.
You can change the columns that appear in the table for a resource type via the Column Chooser, which is accessed by choosing Home > Columns > Column Chooser.
You also can click the Columns icon (identical to the Column Chooser icon) at the bottom of the navigation panel to display a list of available columns in the navigation panel.
For more information on configuring the Resource Manager and limiting the resources shown, refer to the Resource Manager Display Characteristics topic.
You can:
Create a new resource of the selected type by choosing Home > Edit > New.
Open an existing resource for viewing and/or editing by double-clicking the resource row in the table or by selecting the resource row in the table and choosing Home > Edit > View.
Duplicate an existing resource by selecting the resource row in the table and choosing Home > Edit > Duplicate.
Delete an existing resource by selecting the resource row in the table and choosing Home > Edit > Delete.
Note: A model cannot be edited or deleted when it is still linked to its data source.
With a single resource selected, you can choose Home > Actions > Trace Usage to open the Dependency Viewer, which provides information on where the resource is used and any additional resources that the currently selected resource itself uses.
The Resource Manager provides several tools to make it easier to deal with large numbers of resources.
To find unused resources of the selected type, choose Administration > Selection > Show Only Unused.
You can clear this selection by choosing Administration > Selection > Show All.
To find duplicate resources, choose Administration > Selection > Show Only Duplicates.
In the Select Comparison Criteria window that appears, select the properties that must match in order for the resources to be considered duplicates. For example, if you are looking for duplicate URDs, you might select to compare the model, corrective task and scheduled tasks, but not the URD name. Once you have selected the columns to compare, click OK to show the duplicate resources. You can clear this selection by choosing Administration > Selection > Show All.
You can merge multiple resources of the same type into one resource. This can be helpful when you have, for example, several models that all represent the identical distribution or constant value, or several tasks that are identical. This might happen if, for example, you have imported diagrams that all reference the same model, but the imports happened at separate times; the model would be imported each time a diagram that referenced it was imported. There are two ways to merge resources:
IMPORTANT: For both methods, you should be certain that the resources that you are merging are identical before proceeding. Merging cannot be undone, and only the information from the "target" resource (i.e., the resource that you merge the others into) will be retained.
To merge resources manually, select the resources and choose Administration > Actions > Merge and Delete.
The number of resources that can be selected at once is limited by the value in the Administration > Selection > Max Selection field.
In the window that appears, select the resource to merge the other resources into (i.e., the resource name that will be retained). This resource will be used in all places where the other selected resources were previously used.
To find duplicate resources and merge them into a single resource, choose Administration > Actions > Merge All Duplicates.
You will be asked to confirm that you want to merge all duplicate instances of each resource of the selected type into the first occurrence of the resource. In the Select Columns window that then appears, select the properties that must match in order for the resources to be considered duplicates. Once you have selected the columns to compare, click OK to merge the duplicate resources.
Note: If you are merging models, they must be of the same category in order to be merged. You cannot merge models that were created via publication.
To print the contents of the Resource Manager, choose Home > Edit > Print.
You can send the contents of the Resource Manager to Excel by choosing Administration > Actions > Transfer Report.
In the Transfer Report window that appears, you can select to export either the current item (i.e., the table for the currently displayed page) or the full report (i.e., the tables for all pages in the Resource Manager). If you transfer the full report, each table will appear on a new tab in the Excel file, and you will be prompted for a filename and location. The Excel file will open automatically if the software is installed on your computer.